Time to Paint & Nail! UPDATE

NOTE: PAINTING JUST GOT MOVED UP ON THE SCHEDULE! They now tell us we can get in as early as Thursday, February 15. Can you help? See below. Thank you!

The Gathering Place is getting closer to being operational! Crews from Millennium Construction have been working hard, crews are in and around the building nearly every day.

Many of you have been asking how and when you can help with the Gathering Place. That time is now, and you can help save Camp Zion money. We are responsible for several upcoming portions of the project, which have to happen during certain windows of opportunity to keep the building on schedule.

Skilled labor is always helpful, but if you can take orders, we can provide you with meaningful work to help us accomplish the task.

NOTE: Construction schedules sometimes change unexpectedly, but at this moment, we anticipate that the schedule will look something like this:

PAINTING

  • Feb 15-20 : Prep work: masking, protecting surfaces, etc. Possible primer application.

  • Feb. 20-22: Primer coat

  • Feb. 22-26: Finish coat

  • Feb. 26-27: Touch up, clean up

FINISH CARPENTRY & TRIM

On a similar note, we need help with some finish carpentry and trim soon after painting is done, or maybe even simultaneously.  Dates are a little less clear, but it is looking like early March. We  will need people who can cut and nail, under direction from a qualified foreman.

  • Feb. 26-March 1 OR SOONER: Finish carpentry and trim

  • Break for the Spaghetti Supper Silent Auction Weekend in Zion

  • March 4-9

  • March 11-15

Please message us ASAP at office@campzion.com or call the camp office at 920-854-2790 if you can help. We will do our best to house and provide at least two meals daily. Housing is limited, since we will have groups on camp over both February weekends.

We would be grateful for your assistance. Thank you!

Camp Zion